Cisco Switching/Routing :: Replacing 3750 24 Port With 3750 48 Port?
May 21, 2012
We have a stack of switches that is at the max number of members allowed in the stack. Problem is we are running out of port density and need to add more ports. So instead of adding a whole new stack I would rather replace 2 of the 24-port swicthes with 48-port switches.
If the two 24-port swicthes we are removing are stack members and neither of them are the stack master, I should be able to replace the 24-port switches with the 48-port switches without bringing the master offline? If the new 48-port switches are running the same IOS version as the current 24-port swicthes, they should add themselves to the stack?Would I have to tell the new 48-port swicthes what switch numbers they are replacing in order for them to be added to the stack since we are at the max number of members?Also since the 48-port swicthes are replacing 24-port switches will the master give the 48-port switches the configuration for only the 24-ports?
View 11 Replies
ADVERTISEMENT
May 19, 2013
I have a stack of 4 3750 Switches.
1. WS-C3750G-12S
2. WS-C3750G-12S
3. WS-C3750X-48P
4. WS-C3750X-48P
The stack cable connected to Switch 1 Port 1 and Switch 4 Port 2 will not come back online. The logs show that there was a Stack line change. I have replaced the 1 meter Stack cable from Switch 1 to Switch 4 three times and it still does not come back online. This is the part that is interesting.. I have disconnected Port 1 Switch 4 and connected it to Port 2 Switch 4 and then Switch 4 came back online. This made me think Port 2 on Switch 4 was working correctly. Then I disconnected Port 2 Switch 1 and connected it to Port 1 Switch 1 and then Switch 1 came back online.
View 1 Replies
View Related
Mar 11, 2013
have a cable i think is bad, is it possiable to switch the cable out without causing any downtime to the switch or connected devices?
HQ-1st-Flr-Stack#show switch stack-ports summary
Switch#/ Stack Neighbor Cable Link Link Sync # In
Port# Port Length OK Active OK Changes Loopback
Status To LinkOK
[Code].....
View 15 Replies
View Related
Nov 7, 2011
I am trying to configure a 3750 48 port switch and having trouble with getting it to see the sfp. I just want to set up the router with a pretty basic set up since I am using it for a ping test between 2 buildings, via fiber. How I can enable the sfp port?
View 3 Replies
View Related
Mar 10, 2013
In my MDF I have a 4stack of the WS-3750-48P switches. Is it possible to replace one with a C3750X48PF-S with out causing any issues? Or would it be better to just have 3 stacked and trunk this one to the core 4506. Keeping in mind I bought this one to expand the port number for one of our remote offices.. I would hate to send them the gig switch when there isn't as much usage..Besides if I can get my CFO on this switch he might authorize me to replace the rest... He is reticent to believe it makes really all that much of a difference.
View 2 Replies
View Related
Jun 3, 2013
I was wondering what general steps might be taken in order to "replace two(2) 3750 (stacked) with one (1) 3750X - Server Access". General steps and what I might have to do configuration wise. I know i'm copy pasting the existing configs into the new switch, but are there any caveats?
View 5 Replies
View Related
Jun 18, 2012
I have configured SPAN in cisco 3750 switch as below mentioned. but the destination port protocol is down.switch(config)#monitor session 1 source interface gigabitethernet1/0/1switch(config)#monitor session 1 destination interface gigabitethernet1/0/11 ingress vlan 1
View 8 Replies
View Related
Dec 12, 2011
Been dealing with a strange problem for several days now. It started out with a problem that I thought was VTP related but ended up being something else. I setup a span port on a 3750 that I am connected to that was mirroring the trunk connection coming into the switch.
Never saw an VTP traffic come across the connection but doing a sh vtp status indicated the traffic was arriving and getting processed. When I found some debug commands (debug sw-lan vtp), I was also able to see the packets go between switches. Seeing this issue concerns me that there is other traffic that isnt showing up during a span session.
I know that doing a span on a switch, especially using a trunk port as a source, isnt a good idea. Since I didnt have a TAP at time, this was my only choice. I have since borrowed a NetOptics TP-CU3 tap from a good friend and was able to confirm the VTP traffic was going across the trunk connection between switches.
All of my 3750's are running 12.2.55.SE.
View 8 Replies
View Related
Dec 7, 2011
I have 3750 core/distribution switches with routing enabled in two offices connected with copper link and L3 port channel interfaces. NewOffice#2 has moved about 5 miles farther away from office#1 and I have to deploy new core/distribution switch connect it to old core#2 via F.O and move all access switches with it. Old core will stay in old #2 offices as a bridge between office#1 and new office#2 Office#1core<->copper (Ethernet) <->oldoffice#2core<->f.o. <->new office#2core How I should configure port channels ports on oldoffice#2 core to act as bridge between office#1 core/dist and newoffice#2 core/dist without changing anything else (ip, etc) on whole network
View 1 Replies
View Related
Apr 15, 2012
There 's a Cisco IP phone that sits between a PC and the switch port. On the switch port, no MAC address is learned. However, the switch is able to detect the IP phone and deliver power to it: [code] Switch is Catalyst 3750 with IOS version 12.2(58)SE1.
View 1 Replies
View Related
Jun 5, 2012
We have several 3750 stacks across our campus that we are unable to completely clear port security on. We have mac address stick set up on all access ports. When we clear the sticky address on the port, the mac address is removed from the running config like normal, but we keep getting port-security voilations. If port security is taken off the port completely, i.e. no switchport port-security, traffic still doesn't pass the port. Even clear port security across the stack doesn't work. If we try to reload the stack, only the master reboots, and the other switches in the stack lose switch capabilities.
View 1 Replies
View Related
Dec 15, 2011
I have a non-cisco router with a public WAN address. This is conencted to a 3750 switch internally. The switch is the default gateway for all VLANs, and the gateway router has static routes back to the 3750. The Router provides NAT, no NAT is done on the switch.My requirement is to port forward port 29 000 so that I can access a server on VLAN4 via this port.
So, I have: Router: Port 29000 map to 192.168.4.1 (Switch VLAN4 address)
The question is, how do I route port 29000 from the 3750 to the server on 192.168.4.42 ? what exactly I should add in order to port forward port 29000 incoming form my router, to my server on 192.168.4.42.
View 17 Replies
View Related
May 24, 2012
I would like to ask about 3750 stacking and some Cat6 stuff...
1) How do we monitor 3750 stacking port in LMS?
2) Let say if I stack 3 switches, middle switch should be Master. Uplink should be at Top and Bottom. Is best practice?
3) Can we mixed 3750G and 3750X and what is result internal BW - fallback to 32Gps?
4) is there any Qos difference between WS-X6816-10G-2T and WS-X6816-10G-2TXL?
5) is there any Qos difference between MSFC5 PFC4 and MSFC5 PFC4XL?
6) What is main difference between PFC4 and PFC4XL in Sup2T?
7) Pls share more about Central and Distributed Switching in Sup2T and which card support Distributed DFCXL?
View 3 Replies
View Related
Apr 24, 2012
We have computers that are connected to a switch stack of 3 - 3750 switches. Randomly, we experience pcs that fail to communicate on the network. At first thought I figured the port went into err-disabled state, however the port shows up fine on the switch and moving the pc to another port on the same switch in the stack fails to fix the problem. To add to the confusion, if I immediately connect a different machine into the problematic port the newly connected machine has no issue and operates normally. Connecting back the first machine still results in no connectivity.
The only way to gain back network connectivity is to move the pc to a different switch in the stack. shut/no shut doesn't work.The IOS the stack is running is 12.2 and the switch ports are configured using cisco port macros.
here is how all the ports are configured.
switchport mode access
switchport port-security
switchport port-security aging time 2
switchport port-security violation restrict
switchport port-security aging type inactivity
macro description cisco-desktop
spanning-tree portfast
spanning-tree bpduguard enable
View 5 Replies
View Related
Feb 7, 2011
I have a stack with a lot of stack-port changes, but on all the ports, how can I determine the faulty switch in the stack, cables are already verified. We did also a restart of the whole stack power off/on
running version
WS-C3750-48P 12.2(55)SE C3750-IPBASEK9-M
This is the output after 6weeks
Switch#/ Stack Neighbor Cable Link Link Sync # In Port# Port Length OK Active OK Changes Loopback Status To LinkOK -------- ------ -------- -------- ---- ------ ---- --------- -------- 1/1 OK 4 1
[Code].....
View 7 Replies
View Related
May 23, 2012
I'm trying to configure a mirror port on a 3750. This configuration needs to replicate data from local ports, but I need that also act as a regular access port.
With the initial configuration, SPAN port, there is no problem, all the data of the configurated ports is replicating in the configurated port. On the port configurated as mirror there is a PC connected for audio recording. When the port is not operating as SPAN there is communications without problem over the LAN. But when I configure the port as SPAN, communication is interrupted.
Here is the actual configuration:
SWITCH1-PISO7#sh monitor session 1
Session 1
---------
Type : Local Session
[Code]......
View 5 Replies
View Related
Jan 22, 2012
I set up a port-channel trunk between a acess switch 3750 ( int gi2/0/1 and gi2/0/2) and Core 6509( int gi7/11 and gi7/12).
On the both the 3750& 6509 I configured:
interface Port-channel15
switchport
switchport trunk encapsulation dot1q
switchport trunk allowed vlan 100,103
switchport mode trunk
But the ports on the core g7/11 and g7/12 keep shutdown and when I do show interfaces port-channel 15, it show the interface is shutdown.
View 6 Replies
View Related
Dec 18, 2012
The stackwise marketing info states that when a failed member is replaced with a new switch the replacement switch "gets the exact configuration of the old device". I would figure it takes a little more than just disconnecting and connecting a new switch in the same spot on the stack. doing this with 3750 family switches? What are the steps to prepare the stack for a new member? what steps need to be taken on the replacement switch before insertion into the stack to make sure it gets configured like the unit it was replacing?
View 5 Replies
View Related
Feb 27, 2013
I am building a new network and intended on using the min-link feature on my port-channels between a 3750-X series switch and Nexus 4k.
However reading further into this it seems this feature is only supported on higher end models. I cannot find any reference to the min-links feature in the 3750-X configuration guide. Is this an available feature?
The 3750-X model is WS-C3750X-24T-L running IOS 12.2(55)SE3 IP Services
My thoughts is that the is only an LACP supported feature so I may not see the command until I have entered an LACP specific command on the port-channel but unfortunately I do not have a 3750X to verify this on at present.
View 0 Replies
View Related
Nov 6, 2012
I have a 3750 catlyst switch in my network and it is like a distubation switch,And for the nating and dhcp nomadix is using as gateway in the same network. for one of my local PC i need to config the port forwarding in 3750 switch. How to config the port forwarding on 3750 switch,
View 3 Replies
View Related
Nov 8, 2011
I'm trying to setup a port on a catalyst 3750 so it will pass traffic for 2 vlans. It connects to a (watchguard) firewall which I've configured with a primary IP (for vlan 27) and a secondary IP (for vlan 29).
However I can't seem to find the correct commands to enter on the cisco switch port (I've tried a variety).
FYI the current configuration is...
interface FastEthernet1/0/38
description ## Connection to WG vlan27 and vlan 29 ##
switchport trunk encapsulation dot1q
[Code].....
View 8 Replies
View Related
Oct 7, 2012
We have QoS configured throughout the company, but the standard config we have applied across the 3750 switches only includes the below: We have IP phones (not cisco) attached that are marking with EF, and the PC is an untrusted end device (so needs to be by default marked as zero).Is the above enough to trust VOIP DSCP EF without resetting it to DSCP 0, or do I also need to add a trust line (i.e.: mls qos trust dscp)?
View 2 Replies
View Related
Mar 27, 2013
On 45XX catalyst , bandwidth is allocated across six 8-port groups, providing 1 Gbps per port group. Example for the following line card : WS-X4448-GB-SFP
I want to know if there is the same mecanism on 3750X switches. I mean is bandwidth allocated across a group of ports like on 4500 catalyst ?
View 5 Replies
View Related
May 13, 2012
We have a switch that, when configuring auto qos on and edge port facing video equipment, the upstream port channel drops. I was wondering if no auto qos would have to be configured on the member ports of the port channel prior to enabling auto qos on any other ports.
View 2 Replies
View Related
Jun 29, 2012
We have a number of 3750 stacks used as access layer switches connecting Siemens VOIP phones and then a PC that connects to the phone.
For example if I plug PC A to the phone that connects to port 13 I pick up an IP addressand all works as predicted now if I plug in PC A to any other VOIP phone that connect to another port on the same switch it goes in error disable state ITs like the switch is holding my PC mac address and locks it down with the port which in my case is Gi2/0/13.
interface GigabitEthernet2/0/13
switchport access vlan 726
switchport mode access
[Code].....
View 7 Replies
View Related
Oct 3, 2012
Is it possible to rate limit on a L2 trunk port on a 3750?
current port config and ios are as follows;
interface GigabitEthernet1/0/50
description *** Connection to Fiber Link ***
switchport trunk encapsulation dot1q
switchport trunk allowed vlan 1,172
switchport mode trunk
end
flash:c3750-advipservicesk9-mz.122-46.SE.bin
i was wondering if the "srr-queue bandwidth limit 10" command would work to limit the output from this interface to be 10 % of the port bandwidth and then the same command could be done on the other side.
View 1 Replies
View Related
Jun 18, 2012
We would like to setup a link to our DR site that is separate from our main network traffic. This link will be used by an EMC VNX SAN for replication traffic. The SAN will be plugged into a fiber port on a 3750 switch and going out from the same switch (going in as multimode, going out as single mode) into a patch panel that runs over to the DR site (about a mile away). At the DR site it will go from the fiber panel into another 3750 switch which ends up going back out of that switch into our DR SAN.
I'm wondering what the best way would be to configure the fiber ports to accomplish this. I'm affraid that the replication traffic will find it's way over through another route and congest our main network unless configured appropriately.
View 4 Replies
View Related
Apr 23, 2012
I would like to know how many port channel can i configured in the switch 3750 X ? and if there is a limitation by IOS ?
View 4 Replies
View Related
Aug 15, 2012
I am experiencing the same problem described in this post {URL}. I have seen this happen on different networks, with different equipment attached. It happens on both 2960 and 3750 switches. Basically the connection drops, and we see in the web interface "Port is Disabled". This appears to happen every 10 minutes.
On the CLI, the status shows as connected.
Port Name Status V lan Duplex Speed Type
Fa0/38 connected 1 a-full a-100 10/100BaseTX
I have ran cable diagnostics while the drop out is occurring.
Interface Speed Local pair Pair length Remote pair Pair status
--------- ----- ---------- ----------------- ----------- -------------------
Fa0/38 100M Pair A 28 +/- 15 meters Pair B Normal
[code]...
During the outage, I see the duplex fluctuate between full and half. The outage occurs for approx 90 seconds. If I fix the duplex and speed at both ends, the outage reduces to around 30 seconds. If I apply spanning-tree port fast the outage reduces further to around 10 seconds. Before I change any configuration on the port, the logs show the interface going down
Aug 16 13:06:51.875: %LINEPROTO-5-UPDOWN: Line protocol on Interface FastEthernet0/38, changed state to down
Aug 16 13:06:52.874: %LINK-3-UPDOWN: Interface FastEthernet0/38, changed state to down
[code]...
However, once I apply the configuration nothing is logged. However we can still see the connection is disappearing for around 10 seconds. I suspect the issue wasn't resolved for the person reporting the problem in the link above, but because the outage is minimized, and not being logged it is going unnoticed.
View 30 Replies
View Related
Jul 27, 2012
I have the task of replicating the router config on a 3825 router on a 3750 switch. Reason is we are taking out the router and replacing it with the switch to make use of the router for other functions.
Below is main part of the router config:
!
ip source-route
ip cef
!
!
multilink bundle-name authenticated
!
license udi pid CISCO3825 sn FCZxxxxxxx
!
vlan internal allocation policy ascending
[code].....
The 3750 switch I have runs C3750E-UNIVERSALK9-M, Version 12.2(55)SE3 on a LAN BASE license.
The first thing I have done is to order for a license upgrade to IP BASE which would give the support for OSPF routing.I do not see much of an issue with the Interface configs, however, I am not too sure about replicating the routing config on the switch.
My question is can I run the commands as shown for the OSPF routing on the switch? If not, can I get suggestions on how best to set this up on the switch?
View 4 Replies
View Related
Oct 27, 2011
If i fully populate all switch port (Cisco 3750 series) with 100 filter list on each port is it recommendable.
View 4 Replies
View Related
Apr 11, 2012
I would like to configure a 3750 switch port to be able to use two vlans. I know you can do this with a voice and data vlan, but what about two data vlans ? Say I have two devices, one on a 10 subnet and the other on a 172 subnet, but i only have one wall jack for both devices to plug into. So I use a mini switch to connect both devices and connect the switch to the wall jack; and of course this all leads back to one switch port. When I go to enter the switchport access vlan 172 cmd, how would I also make it so the device on the 10 subnet could route out ?
View 9 Replies
View Related
May 10, 2013
In our company 3nos Cisco 3750 (WS-C3750-48P) access switch in stake mode. All port are assigned with voice and data Vlan also Avaya IP connected with this switches. From last few days tow port 2/0/7 and 2/0/8 is showing amber and status is showing err-disable. At Avaya end it is showing a message “ETHERNET WAITING” in phone dispaly. I try to connect laptop directly with these ports but it is showing "Cross Connectivity". [code]
View 4 Replies
View Related