I have 3750 stack with 4 switches.I am trying to make change some port to new VLAN, but switch 2 & 3 new change never works, the ports stick with old VLAN. Other two switches works as I expected on new changed VLAN.Tried to reboot, no progress.

#Show VLAN command confirmed the VLAN changes are made.
#show switch detail
Current
Switch# Role     Mac Address     Priority     State
--------------------------------------------------------
1       Member   0019.e752.xxxx     1         Ready
2       Member   0015.f9bf.xxxx    1         Ready

[code]......

View 4 Replies


ADVERTISEMENT

Cisco :: CiscoView Not Displaying All Switches In 3750-Stack

Apr 17, 2012

I am running LMS 4.1 and have an issue with Inventory: I have a stack of four 3750 switches, but only two of them are showing up in CiscoView. If I right-click - Topology - Device Report ;  I see all four switches. The switches are standard 3750 switches and should be included in the Device Packages for CiscoView
 
Also if I go Reports  - Detailed Device ; I see the same two devices show up under Module Information. However when I go to Reports - Device Attributes ; I see all four devices correctly displayed.
 
I have tried and deleted and added the stack in CiscoPrime, but with same result.

View 3 Replies View Related

Cisco :: 3845 Enabled For CDP Connected To A Stack Of 3750 Switches

Oct 20, 2009

I have a 3845 enabled for CDP connected to a stack of 3750 switches. From the router, i dont see any CDP neighbors. From the switch, i can see the router as neighbor. Why isn't the switch showing as a neighbor from the router side? [code]

View 3 Replies View Related

Cisco WAN :: 3750 Layer3 Switches - Connect Them Via Stack Cable

Jul 11, 2012

I have two 3750 layer3 switches and I need to connect them via stack cable.so if I connect them with the stack they will be act as an one switch, but for the configuration if I create a VLANs on the master switch (applied all the configuration on the master one) this configuration will be transfered to the slave one or I have to repeat the configuration that I did on the master.

View 5 Replies View Related

Cisco Switching/Routing :: 3750 - Running 7 To 9 Switches In One Stack

Aug 6, 2012

Looking for feedback from other organizations that have large 3750 stacks.  I've got one stack of (8) 3750's composed of (6) 3750G's and (2) plain 3750's.  This particular stack is usually unresponsive to SNMP queries and often fails to write config when we make changes.  After a couple tries it will finally go.  Part of my probably here is likely the plain 3750's that always boot faster and come up as the master.  I should manually set the master to one of the G's.  What I'm wondering is who else has 7-9 3750's stacked and are they performing well for SNMP, telnet, etc?  I've got another newer stack of 7 3750E's that I need to add one more switch to.  Need to decide if I want extended downtime to break the stack up or just add the 3750X to make member 8 and hope it performs well.  I have 50+ 3750 stacks working great on our campus.

View 1 Replies View Related

Cisco Switching/Routing :: 3750 Stack Switches IOS Upgrade?

Nov 13, 2012

I am trying to do ios upgrade on 5 stacked 3750 switches. All the switches have different model number, so i am wondering which image file i should download. As far as i understand all the stacked switches should have the same IOS, i may be wrong. The switches have the following model numbers and SW images;
  
Switch   Ports  Model              SW Version              SW Image
------   -----  -----              ----------              ----------
     1   28     WS-C3750G-24PS     12.2(35)SE5             C3750-IPSERVICESK9-M
*    2   28     WS-C3750G-24PS     12.2(35)SE5             C3750-IPSERVICESK9-M
     3   52     WS-C3750G-48PS     12.2(35)SE5             C3750-IPSERVICESK9-M
     4   30     WS-C3750E-24PD     12.2(35)SE5             C3750E-UNIVERSAL-M
     5   30     WS-C3750E-24PD     12.2(35)SE5             C3750E-UNIVERSAL-M
 
which image file i should use as they all have different model numbers and Cisco provides different image files for each model.

View 18 Replies View Related

Cisco Switching/Routing :: 3750 Stack Switches Not Showing Up

Jan 27, 2013

We have several stacks of 3750 switches where this problem is occurring.  All of the switches are running IOS version 12.2(50)SE3.  (Yes, I know it's old.)
 
We're seeing inconsistency in how the stack reports members when issuing the following commands:
 
sow switch
show version
show inventory
 
Not all members are showing up in the output of the "show version" and "show inventory" commands.  For example:
 
HUNTI-WV-WDAC03#sh switch
                                           H/W   Current
Switch#  Role   Mac Address     Priority Version  State
----------------------------------------------------------
1       Member 108c.cff2.ea00     15     0       Ready              
2       Member 8cb6.4f0a.a600     1      0       Ready              
*3       Master 8cb6.4f0a.9c00     1      0       Ready
(all three switches in stack are displayed)(code)

View 1 Replies View Related

Cisco Switching/Routing :: 3750 - Etherchannel Across 2 L3 Switches To Stack

Mar 26, 2012

I am wanting to etherchannel from a 3750 stack to core Layer 3 switches (also 3750) with a cable going to each core switch, I have put both core switches and the stack under a 28bit subnet mask, but I dont seem to be load balancing across both links.

View 5 Replies View Related

Cisco Switching/Routing :: How To Add Four 3750 Switches Into Existing Stack

Sep 22, 2012

I have 3 3750  staking switch with the following configuration:

                                            H/W   Current
Switch#  Role   Mac Address     Priority Version  State
----------------------------------------------------------
1       Member 442b.0350.9400     1      1       Ready              
2       Member 442b.0357.8780     2      1       Ready              
3       Master 442b.036f.a800        3      1       Ready              
 
The new switch is installed to be wired to the master switch. the swtich 3 (* 3 Master Ready 442b.036f.a800)my question is: if you disconnect the wiring from the master stack to connect to the new switch, it is possible that the new switch change the current configuration of stacking.
 
-Can I just add the new switch with clean configuration without changing the current configuration ?
-How is assigned the stack number? i need the new switch be with the GI4 / x?. I can I manually by assigning ports?
-If I want to the new 3750 member witch lower prioridad, can I change priority before adding to stack?

View 2 Replies View Related

How Does Cisco Prime NCS Handle The Device Licenses For Stack Of 3750 Switches

Nov 25, 2012

before I open a TAC case: How does Cisco Prime NCS handle the device licenses for stack of 3750 switches? Just one device license for the stack or a license for every physical switch in the stack? I can't find a answer on the Cisco website, but maybe one of you knows it from a deployment you have done..

View 2 Replies View Related

Cisco WAN :: 3750 - Access Switches Not Accessible When Stack Member Got Rebooted

May 20, 2012

We have got 2 3750 switches in the stack which are connected to access switches with 2 uplink ports .  each 1 uplink from each physical stack switch .
 
Due to some power issue our member switch got rebooted. After the reboot the access switches were not reachable through ping , but i was abe to see access switches in "show cdp neighbour" .   Then i rebooted the master switch and member switch one after other . after which i was able to ping the access switches.
 
IOS Version : c3750-ipservices-mz.122-35.SE5.bin

View 3 Replies View Related

Cisco Switching/Routing :: 3750 - How To Remove Stack Info On 2 Switches

Feb 20, 2012

I have been given 2 x 3750 switches that were a stack, I need to keep the configs on both but how do I make them individual switches again and remove the stack info?

View 3 Replies View Related

Cisco Switching/Routing :: 3750 - Actual Frame Path Between Switches In Stack

Feb 12, 2013

Lets say i have 2 3750 switches stacked via backend stack cables. Now if a packet needs to go from 1 switch in the stack to second switch in the stack, will it travel via stack cable or do we need to connect both switches via uplink ports (ethernet or sfp). I tried reading datasheet but it no wheres mention the actual frame path between switches in stack.

View 3 Replies View Related

Cisco Switching/Routing :: 3750 Stack Switches Compared To 4500 Series

Dec 30, 2011

I'm thinking about using a 3750 stacking around 4 or 5 switches intead of using one 4500 series switch.
 
1-My first argument was concerning the budget (one 4500 instead of four or five 3750 in stack mode) ---- Here i think 4 or 5 stacked 3750 is cheap than one 4500
2- My second argument was about harware redundancing that i don't have with one 4500 and that i have with stack mode ----Here i have more hardware redundancing with 3750
3- The bug that we notice today in 2960 and 3750 and not in 4500
4- Simple to manage a 4500 compare to 3750 stack design
5- I was looking also for the one with best backplane ----Here i didn't have any infos concerning the best backplane between 4 or 5 stack 3750 and a 4500.
6- I'm also looking for power redundancing.

View 5 Replies View Related

Cisco Switching/Routing :: 3750 Stack To Upstream ISP Separate Switches - MAC Flapping

Mar 11, 2012

I have an issue with a Cisco 3750 switch stack which is connected to two seperate upstream Cisco 3750's which are administered by an ISP.  The ISP is experiencing MAC address flapping from one of my VLAN SVI's i am using to route traffic upstream
 
[code]...
 
As you can see I utilise a VLAN SVI to route traffic to the upstream 1.1.1.2 (illustration only) IP.  As per the diagram of the topology attached, the ISP is receiving a MAC address flapping error confirming the SVI MAC address from my switch stack is being learnt on the trunk port connecting switch 1 and switch 2, and also the port (Gi1/0/48) directly connected to my switch stack. As these are all Layer 2 links essentially being passed upstream and then connected between the two ISP switches, we have a 3 way triangular loop formed.
 
If I was to remove the port channel configuration from the two ports associated with the VLAN SVI, am i right in suggesting this would still form a layer 2 loop?  The two ports would still be a member of the SVI VLAN, and it is the VLAN MAC address which is being learnt by the two ISP switches on different interfaces.

View 2 Replies View Related

Cisco :: Connecting And Configuring Two Wlc In High Availability To 3 Switches In Stack 3750 In Difference Ports?

Aug 1, 2011

Is possible connect and configuring two cisco wlc in high availability to 3 switches in stack 3750 in difference ports?For example
 
WLC A (Primary) - SWITCH MASTER
WLC B (Secondary) - SWITCH SLAVE
 
How can i connect the wlc's in HA to get a redundancy in the stack?

View 8 Replies View Related

Cisco Switching/Routing :: Configure 3750 Stack As Core / 2960 As Access Layer Switches

Sep 29, 2012

I configure 3750 stack switch as core and 2960 stack switches as access layer switches.I connected my laptop to one of my core stack in VLAN 10 and I am pinging to one of my server in VLAN 1. What will be the minimum latency at the time of inter VALN routing

View 2 Replies View Related

Cisco Switching/Routing :: Output Queue Drops On 3750 Core Stack And 3560 Edge Switches

Jan 10, 2013

I've been fighting what seems to be an increased number of outqueue drops on our core stack and edge switches for the last 3 or 4 weeks.(The core consists of a stack of 5 3750s in 32-gig stack mode. The wkgrp switches are 3560s. all are at 12.2.52) The  wkgrp switches are directly connected to users. We use Nortel IP phones with the phone inline with the user PC. auto-neg to 100/full. [code] However I have tried turning off QOS on a couple of workgroup switches (no mls qos, but left individual port configurations the same) but am still seeing drops.Since I have disabled qos on the switches in question (no mls qos)  (not the core tho) I am presuming these commands have no affect on the switch operation and therefore cannot be related to the problem. With QOS turned off one would presume that it is general congestion - especially at the user edge where busy PC issues might contribute. So I wanted to see if I could see any instances of packets in the output queues building up.
 
 I wrote some scripts and macros that essentially did a snapshot of 'show int' every 20 seconds or so, and looked for instances of 'Queue: x/' where x was greater than zero.What I found after several days of watching the core stack, and a few of the workgroup switches that are most often displaying the behavior, was that I NEVER saw ANY packets in output queues. I often saw packets in Input queues for VLAN1, once in a great while I would see packets on input queues for fa or Gi interfaces, but NEVER on output queues. [ code] Additionally, when I look (via snmp) at interface utilization on interfaces showing queue drops (both core and wkgroup), they are occurring at ridiculously low utilization levels (as low as 4 to 8%). I've tried to look for microbursts between the core and a wkgroup switch where the core interface was experiencing drops, but haven't seen any (using observer suite). [code] While the queue-drop counts aren't critically high at this point, they are happening more frequently than in the past and I would like to understand what is going on... In most cases, no error counters are incrementing for these interfaces. Is there some mechanism besides congestion that could cause output queue drops?

View 4 Replies View Related

Cisco WAN :: Replacing A Stack Master In 3750 Stack?

Jan 22, 2013

We currently have as our stack master a 24 port Non-PoE that we want to replace with a 48 port Non-PoE. The 48 port switch at one time was provisioned as switch 3 in the stack (not the master). Correct me if I am wrong, but theoretically all I should need to do to get this working is to shut off the existing master so it re-elects a master and then provision the 48 port switch as the new switch one and make sure switch 1 has a high priority?
 
Do I need to write erase the switch that is replacing the current master first?          

View 4 Replies View Related

Cisco Switching/Routing :: PBR - 3750 VLan Does Not Accept IP Policy Route-map

Nov 1, 2012

I am trying to configure policy based routing however when i try to apply to an interface vlan.  The configuration does not show in the interface.
  
route-map OTHER_ROUTE permit 10
match ip address OTHER_ROUTE
set ip next-hop x.x.x.x

[Code]....

View 4 Replies View Related

Cisco Switches :: SGE2010 Can Use 4 SFP Ports And Stack Of Two Switches At Same Time

Feb 15, 2012

I looking to buy SGE 2010 swith, but I have some question:

1. Can I use 4 SFP ports and stack of two switches at the same time.
2. Is it possible to use for stacking  ports other than 24, 48?
3. What is maximum possible number of ports  to use for stacking (can I get more than 1Gb thruput).

View 0 Replies View Related

Cisco WAN :: High CPU On 3750 Stack?

May 1, 2011

I have been seeing high CPU on a 3750 stack we use for our phone system. I followed the documentation here:
 
[URL]
 
This documentation pointed out that the interrupt was very high and so I started looking at the CPU queues to debug. The icmp queue was dropping TONS of traffic.
 
The debug was full of these:
 
ICMP-Q:Dropped Not a candidate: Remote Port Blocked L3If:Vlan248 L2If:GigabitEthernet1/0/17 DI:0xB4, LT:7, Vlan:248   SrcGPN:17, SrcGID:17, ACLLogIdx:0x0, MacDA:001a.a1c4.1cd2, MacSA: 0013.192c.bb80   IP_SA:5.1.1.10

[Code].....

View 2 Replies View Related

Cisco LAN :: Four Member Switch Stack 3750

Apr 16, 2013

We have a current 3-stack 3750 ( 48-P,48-TS & 3750v2-48PS ) running fine. There is a plan to introduce a fourth stack member ( 3750X-48P ) into this stack.as per cisco documentation, it suggests to use 3750X as master for a mixed stack. In this case, we will need to upgrade current other 3 stack switches to a latest version.,Can we do a no-downtime ios upgrade on the existing 3-switch stack?, when this upgrade is done, is there any way to have the new ios pushed down to all three stack members at the same time or do we need to each member upgrade seperately?, for adding the fourth member, is it acceptable if master is ruuning ver eg. 12.2(55) and all rest of the members run ver 12.2(53) ? will this create any issues and will stacking be successful.

View 5 Replies View Related

Cisco :: Upgrade Version With 3750 Stack?

Oct 30, 2012

I have 4 switches of 3750. I need toupgrade all the switches, but I can't to disconnect the stack cable.How I can to upgrade the version without to disconnect the stack cable?

View 2 Replies View Related

Cisco Firewall :: ASA Redundancy With 3750 Stack

Oct 4, 2011

I will be installing a new ASA 5510 firewall on our SIP vlan to separate our voice traffic from the rest of the traffic.  I'm trying to decide whether or not I should go with an active/active setup or an active/standby.  Any insight on the best way to set this up?  This install is going in from scratch, and I am going to be connecting to a 3750 switch stack.  Should I pair up a link from each switch to each 5510 using etherchannels?  Should I use 8.3 or 8.4?  Most of the docs I've been able to find say it depends on this, that, or the other.

View 2 Replies View Related

Cisco :: 3750 SNMP Stack Monitoring?

Oct 3, 2006

I am building a few 3750 stacks, I want to be able to poll/monitor each individual switch in the stack but as it only has 1 ip associated with the stack how can I do this.  I am polling the uplink interfaces but as I only have uplinks on the top and bottom switch I am blind to a switch going down in the middle of the stack.

View 4 Replies View Related

Cisco WAN :: 3750 - Stack And Switch Port Keeps Going Up / Down

Nov 7, 2012

I have 2 3750x switches connected via a pair of stackwise cables, but I keep seeing error messages about the stack&switch ports going up and down,Performance wise, it seems to work, but I'd like to eliminate this message... Sometimes it will go hours without bouncing, sometimes it does it a few times a minute....
  
*Mar  4 12:56:57.903: %STACKMGR-4-STACK_LINK_CHANGE: Stack Port 2 Switch 1 has changed to state DOWN
*Mar  4 13:16:48.070: %STACKMGR-4-STACK_LINK_CHANGE: Stack Port 1 Switch 2 has changed to state UP
*Mar  4 13:16:49.093: %STACKMGR-4-STACK_LINK_CHANGE: Stack Port 1 Switch 2 has changed to state DOWN
*Mar  4 13:38:55.802: %STACKMGR-4-STACK_LINK_CHANGE: Stack Port 2 Switch 1 has changed to state UP
*Mar  4 13:38:56.809: %STACKMGR-4-STACK_LINK_CHANGE: Stack Port 2 Switch 1 has changed to state DOWN

[code]...

View 4 Replies View Related

Cisco :: 3750 Stack Member Loss Power?

Jun 10, 2012

I have a switch stack with three WS-C3750X-48 switches running 12.2(55)SE. Recently, stack member 3 went offline for a few minutes, after being online for over a year. A show version on member 3 reports that the system returned to ROM by power-on.

Stack member 3 shares a UPS with a router that did not lose power and all three stack members have stack power with four 350 WATT power supplies between the three of them. There are no crashinfo files on any of the switches, log files show the stack ports on the other switches going offline then switch 3 being removed from the stack.

Surveillance recordings show there was no one near the switch during the time and AAA accounting shows no clues. Is it possible the switch crashed without leaving a trace in the logs, a crashinfo file and report that it returned to ROM by power-on?

I've read before that loose stack cables can cause stack member reboots. Would such an event generate log messages other than the stack ports changing states to down?

View 6 Replies View Related

Cisco Switching/Routing :: Adding 3750 To Stack?

Dec 6, 2011

I have two  3750s stacked and one 3750 standalone all in one data closet. The both have the same versions. I want to combine them to make one stack. How do I force the standalone to be the master? sw 1 priority XX(Higher then the existing stack)? Both the stack and the standalone have management addresses. Would it be ok to delete the stack ip address? That way, the standalone(master's address will be the only management address)?How should I connect the standalone 3750 to the stack? At present, the 3750 stack is connected via a cascade cable going from the stack 1 port of the top switch to the stack 2 port of the bottom switch.

View 19 Replies View Related

Cisco WAN :: 3750 Stack Unable To Save Config

Jul 4, 2012

I have a 3750 stack of 4 switches that was installed about 2 years ago. Recently I was doing some work on the switch and realized that I am unable to save the config. I amobviously concerned that if the power fails or the switch reboots I will be reconfiguring it and that is not something I am interested in doing!

[code]...

View 1 Replies View Related

Cisco Switching/Routing :: 3750 Stack Port

May 19, 2013

I have a stack of 4 3750 Switches.
 
1. WS-C3750G-12S
2. WS-C3750G-12S
3. WS-C3750X-48P
4. WS-C3750X-48P
 
The stack cable connected to Switch 1 Port 1 and Switch 4 Port 2 will not come back online. The logs show that there was a Stack line change. I have replaced the 1 meter Stack cable from Switch 1 to Switch 4 three times and it still does not come back online. This is the part that is interesting.. I have disconnected Port 1 Switch 4 and connected it to Port 2 Switch 4 and then Switch 4 came back online. This made me think Port 2 on Switch 4 was working correctly. Then I disconnected Port 2 Switch 1 and connected it to Port 1 Switch 1 and then Switch 1 came back online.

View 1 Replies View Related

Cisco Switching/Routing :: 3750 Stack CPU Utilization?

Feb 20, 2013

i have two cisco 3750 in stack firts, master switch have all swports busy second have only 5 how can i see cpu utilizations of the second switch, and its reasonable to move somme devices from first switch to second for deacreases of cpu and memory utilisatio ns of the master? the stack tehnologies use both cpu as one? or its only for simple management ?

View 9 Replies View Related

Cisco Switching/Routing :: Stack Port Down On 3750

Mar 11, 2013

have a cable i think is bad, is it possiable to switch the cable out without causing any downtime to the switch or connected devices?
 
HQ-1st-Flr-Stack#show switch stack-ports summary
Switch#/  Stack   Neighbor   Cable    Link   Link   Sync      #         In 
Port#     Port              Length    OK   Active   OK    Changes   Loopback
Status                                          To LinkOK   

[Code].....

View 15 Replies View Related