I have two 3750Xs for stack, and i want connect a 2960 switch on this stack with port-channel.I connect 2960 G0/1 to 3750X G1/0/24, and 2960 G0/2 to 3750X G2/0/24. [code] i try to config spanning-tree etherchannel guard misconfig, but no use finally, i have to use "no errdisable detect cause all"..i check the cisco.com, and find a information: for this case, channel-group can use mode desirble.but when i try to change the channel-group in 3750X stack, it shows me that: "with pagp enable, desirble mode must config in the same switch".i try to use mode desirble mode in G1/0/23 and G1/0/24 in 3750X stack, it still can not work.i want to know how to solve this problem? not only do "no errdisable detect cause all".
What I am attempting to achieve is to aggregate trunk ports out of a VMware server into a single logical connection to give as much bandwidth as possible, the switches are 3750X and are three stacked together with the server connections spread across the stack. What I am not sure about is if two port channel load balance protocols can happy co-exist on the switch, by default the switch is using MAC address load balancing and Vmware wants to use IP Source load balancing. As other trunks and channels exist on the switch I don't want to make a change that will affect the other live connections if changing this is a global setting and not local on the channel.
Possible to configure multichassis port-channel between a VSS and 3750X (Port-channel not in the same switch on the 3750X stack). I got it using LACP but I need Pagp to get VSL redundancy “dual-active detection pagp trust channel-group 1”. I am using the last VSS IOS version 15.0(1)SY. I can’t get the option “switch 1 preempt”, has it changed with other option?
I need to tear down an existing port-channel on a 3750X running c3750e-universalk9-mz.150-1.SE3.bin. This port channel is currently down down. It has three ports in it that will be added one each to three existing port-channels, I am assuming as long as the "channel-group" command is exactly the same as it is on the three existing port-channels I should be ok just adding the new port. One point to note is that the three existing port-channels all have three ports so this will be adding the fourth port to each port-channel. I know after reading that it is a best practice for load balancing to use either 2, 4, or 8 ports for a port-channel. Also what is the command to see all ports that are in a port channel?
I have two stacks 3750X on two different sites with two links L_2_L, and I want to configure the port channel to aggregate the two links.
Site A Site B 3750X -A1 --------------------------------------( )--------------------------------------- 3750X -B1 ( L-2-L ) 3750X -A2 --------------------------------------( )--------------------------------------- 3750X -B2
Below the configuration that I have put the two stacks.
site A interface Port-channel5 description Etherchannel group entre le stack 3750X-A et Switch Lan_2_Lan switchport trunk encapsulation dot1q switchport trunk allowed vlan 11,12,999 switchport mode trunk switchport nonegotiate speed 100
But the problem is only one link is Bundeled in channel group, see below
Group Port-channel Protocol Ports ------+-------------+-----------+----------------------------------------------- 5 Po5(SU) LACP Gi1/0/15(I) Gi2/0/15(P)
I have just moved to the 3750X switch and have connected it to a 6509E. From the beginning I was having OSPF encryption errors, followed by flood warnings, LSA issue's, duplicate IP's which is baffling me.
There are no IP's which match on either switch however the 3750X was continually power recycling causing the interfaces drop continually.Even after disconnecting from the 6509 the 3750X continue to behave in the same manner. Could there be some issue with this switch?
i have a VSS core that has 4 downstream links to 4 stacked switches. I connected each of the 4 links to different switch in the switch stack. I then created a port-channel that combines all the links from each switch. Is there any issues associated with this setup?
a Customer ask me to configure a etherchannel between two Switches C3500 XL Version IOS 12.0 follow the first configuration what I done and the output error show me by switch:
There is a cisco ws-c6509,recently it appear error log “%FABRIC-SP-6-TIMEOUT_ERR: Fabric in slot 5 reported timeout error for channel 11 (Module 3, fabric connection 1)”. When I reload the device,the error log disappear.But a few days later,it appears again.I try to replace the slot 3 (WS-X6704-10GE),the error log continues.The IOS version is 's72033_rp-ADVIPSERVICESK9_WAN-M), Version 12.2(18)SXF8"
My C6506 USING ws-sup720-3B, i upgrade the IOS to the latest release of 12.2(33) SXJ1 IOS version. After upgrade and reload the machine got one module cannot be detect..WS-X6416-GE-MT, 16 port 1000mb MTRK ethernet module. The version of this are:
-HW 1.0 -FW 5.3 (1)1 -SW 8.5 (0.46) RFW
Question 1: Any tools available on cisco to check out the hardware/software compabiity feature?
Question 2: Any release note, compability matrix table etc resources.
We have a bit of a problem when deploying VTP v3 in our network. When command vtp primary vlan is issued, switch typically send query to appropriate multicast address in order to find out whether there is already some other one. The problem we are experiencing is that old primary server is not discovered, because it fails to reply on those multicasts.
This debug messages (from the old primary server )may be more describing.
The router 1841 is connected directly to the layer switch. the network diagram is below:
Office A --> Switch (L3) --> Router 1841 --> Internet --> Office B
However, when I transfer the file from Office A to office B, the speed very slow ( only around 40 kb/second), and there are an input error and CRC error:
Cisco-R1841#sh interfaces FA0/1 FastEthernet0/1 is up, line protocol is up Hardware is Gt96k FE, address is 0019.e02f.03dd (bia 0019.e02f.03dd)
I am attempting to add an additional ethernet port on a Cisco 2620 router using a NM-2FE2W card, however the card is not being detected. I read that this card is compatible with this model router, but I have also notice that there is a version 2 of this card. Have I ordered the wrong card or do I possibly have a defective card? My ISO version is 12.2(26) on the router.If this card is not compatible, what is the recommended card for adding an additional ethernet port on this router?
I have issue with my 4510 switch which has got two supervisor engine in single switch.
I am trying find the root cause but not able to ....
Standy supervisor engine is not detecting ....
In show module and bootvar output also , there is error saying " Standby is not up "
show module ouput :
Switch-4510#show moduleChassis Type : WS-C4510RPower consumed by backplane : 40 WattsMod Ports Card Type Model Serial No.---+-----+--------------------------------------+------------------+-----------1 6 Sup V-10GE 10GE (X2),
I have existing cisco 2811 (Version 12.4(3c)). I try to add a HWIC serial card into the router but the new HWIC is not detected. There is no new interfece shows up when i do show run. This HWIC is a new card just bought it.
My management has tasked me to give them a high level overview of the different switching we can choose for our new building.
This is what I know so far.4 Closets, each closet has 450 ports,One MDF room that is will contain one UCS Chassis and a Nimble iSCSI SAN.
I am working on the spreadsheet and it looks like this (Not totally filled):
2960s3560x3750x45064510Approx cost (Each, 48PORT, POE+, 10G uplink, Dual PS, IP BASE) 6K7K8K45K75KMax Capacity192432432192384Backplane speed206464520520ProLeast ExpensiveStackable to 9Stackable to 9ProDual PSDual PSDual PSDual PSDual PSProLayer 3 opt Layer 3 optDual SupsDual SupsConExpensiveExpensiveConNo Dual PSConLayer 2 OnlyCannot stack more than 4 For the MDF I would like to use 2 Nexus 5548's with FEX's, and the layer 3 daughter board. For the IDF's I was thinking of two 4010's.
i cant find any difference in these two devices when i am trying to compare throughput.I need upgrade our new POP and there will be around 4900 MAC adresses in VLAN 150 and 130 MAC adresses in vlan 200.Uplink is 1 gig routed internet connection and there is 14 downlinks to separate villages.i found a few differences for eg stack interface on 3750x but i dont need it.
I have a stack of 2 x 3750X switches these are running 12.2(55)SE5. I needed to add some static IP routes and found that the ‘ip routing’ command is not supported. I came across a document that stated “On switches running the LAN base feature, static routing on VLANs is supported only with Cisco IOS Release 12.2(58)SE and later.” So I have upgraded to 12.2(58)SE2, but ‘ip routing’ is still not a valid command.
The release notes state:“On the Cisco Catalyst 3560-X and 3750-X Series, it adds support for 16 static IPv4 routes in the LAN Base image.”
I have read other posts that talk about running the ‘sdm prefer routing’ command which I have done, but I am still unable to add any routes or run the ‘ip routing’ command.
I have an 1811 with several subnets connected to it.I recently installed a 3750x plant and want to bring my interior routing back to it.
All the routing is handled by the 1811 via secondary interfaces on vlan1?
I have 192 ports, and subnets show up on almost all of them. None of the ports are assigned to any specific vlans. Most ports have several subnets on them.
What is the best approach to getting the 3750x to handle the routing?
my company pay a switch 3750 X. WS-C3750X-24T-E. It uses IP services basically but I failed to configure InterVLAN routing. why interVLAN routing doesn't work on my switch?
When you aggregate multiple fiber GBICs together on the 3508G, do you configure it as an etherchannel, or as fibre-channel? I've looked around online for hours, but can't find it mentioned anywhere.
I was configured ether channel between two cisco 2960s series switches. It is working properly. I was replaced two cables in etherchannel. Now one link working remaining link is down(both cables are working cables only). Below are ether channel details.
I have 3750 core/distribution switches with routing enabled in two offices connected with copper link and L3 port channel interfaces. NewOffice#2 has moved about 5 miles farther away from office#1 and I have to deploy new core/distribution switch connect it to old core#2 via F.O and move all access switches with it. Old core will stay in old #2 offices as a bridge between office#1 and new office#2 Office#1core<->copper (Ethernet) <->oldoffice#2core<->f.o. <->new office#2core How I should configure port channels ports on oldoffice#2 core to act as bridge between office#1 core/dist and newoffice#2 core/dist without changing anything else (ip, etc) on whole network
"How to display the EOBC error counters in the Catalyst 6500 series switches and a definition of the EOBC interface" document here on support forum stays that The Ethernet Out of Band Channel (EOBC) is a half duplex channel that services many functions, which include the Simple Network Management Protocol (SNMP) and the packets that are destined for the switch.
Previously i were thinking that EoBC used only for SCP and SLP protocol. In addition i found other article (but not on cisco site, heh) where stays that The Results bus is a control plane, while the C (EoBC) bus is more of an "admin plane", thus you will never see data packets (such as CDP, SNMP, etc.) going over the R or C bus.
So there is a big contradiction between those two statements. How to prove one of those and if first one right, what meaned under the packets that are destined for the switch in it? SCP and SLP or other traffic as well?
I have 2 Cisco 6509 switches linked together via single Fibre as a trunk.I want to change this to a port channel where I will add another 3 fibre ports to the port channel but what order do I do this to minimise any disruption.
1-Configure PortChannel and add the 3 new ports, this will bring up the Port Channel but what effect will this have on traffic currently going over the single Trunk link? Will spanning tree go mad, how will switches react?
2-Convert existing Trunk link to Portchannel then add in new ports to PortChannel, I guess in doing this there will be a small hit on traffic as it changes to a port channel.
We have 2 6513's that are linked via 2 10 gig interfaces, using an LACP channel.I received an alert this aft stating that the far 6513 was unreachable and the port channel int PO3 had gone down, the 2 10 gig interfaces had also gone down on either side. 5 mins later PO3 had resestablished itself and has been fine since. [code]
running ether-channel mode on. I have a 3120G Blade Switch (stacked). The blade switch connects to the blade servers (internal). Gi1 /0/1 connects to eth0 and gi2/0/1 connects to eth1 on the blade server. [code]
The issue is when is shutdown eth0 on the server, the corresponding interface on the switch (gi1/0/1) does not go down, show up and running.