Cisco Switching/Routing :: 3750G - Adding Additional Switch And Making It Stack
Feb 29, 2012
I currently have Cisco 3750G which is currently live and active and fully populated and only have remote access.
I have an additional same switch which I would like to stack. My initial plans were to have 2 GIbit etherchannels, but I came across the option to Stacks both switch with each other.
When I do a show switch on the live switch its set as a Member: [code]
I would like to add the new switch to the stack without losing the config for the switch which is live. I understand that the highest priority of the switches becomes the Master but as the live switch is Priority 1, would chancing this affect the switches config, or would it lose connection at all?
Also when I plug in the new switch and it reboot how do I ensure it becomes the slave without rebooting the live switch?The cables on the switch do they have to go to port1 on the live switch and port 1 on the new switch or can they be port 1 and port 2?
Our customer has a stack of 6 3750G switches. They want to add another switch to the stack. I tried to quote another G, but I got a warning that the G series is EOS January 30,2013. Can I add a 3750X to the stack? I know that no matter what switch I get, I will have to upgrade the IOS in the stack, as the stack is running 12.2(25)SEE2.
have one 3750G stack with 4 switches and this stack is presenting the follow log message:
%PLATFORM_UCAST-4-PREFIX: One or more, more specific prefixes could not be programmed into TCAM and are being covered by a less specific prefix, and the packets may be software forwarded.
In this stack we are using the layer 3 with OSPF routing, and the current sdm prefer is default:
switch-01-3750#sh sdm prefer The current template is "desktop default" template. The selected template optimizes the resources in the switch to support this level of features for 8 routed interfaces and 1024 VLANs.(code)
I am about rip and replace my current 3750G stack with a 3750X stack. I have trunked over vlan and vtp info and implemented a config so it should be ready to go other then moving cables onto it. However one thing I want to correct with our current setup is that the root bridge on our vlans including vlan 1 is on a separate set of switches that we control, however I would like this new stack to be the root bridge for all of our vlans. It will be the central set of switches that all other switches trunk into. I have pre-set higher spanning-tree priorities for each vlan on the new stack so I expect as I move lines into it that the tree will be re-calculated with it as the root bridge. I've ensured that there are no root guards on any of the other switches trunks and priorities are all at default levels for each vlan. Should I enforce root guard on the trunk interfaces of the new master stack? Most of the trunks are port-channels to the other switches - do I need to set root guard on the Port channel interface or on the individual ports that make up the Port channel? On both? Any other recommendations in regards to implementing spanning-tree with the new stack? I know using port channels eliminates a lot of potential for loops but not every trunk is and I'd still like to have spanning-tree on.
We have a WS-C3750G-24PS switch running 12.2(50)SE , C3750-IPBASEK9-M in production & stand alone and we want to ask a new Cisco WS-C3750-24P running 12.2(55)SE3 , C3750-IPBASEK9-M into the stack with the 1st one.
Just want to know if it is possible and are there any problems with the IOS being different version.
in our network we were using three 3750-48-s switches with stacking one of the switch due to some hardware failure power problem,
now i want to add a new switch 3750-48-s in the existing Stack two switches , the old two switches ios version is = 12.2(25r)SEC the new Catalyst 3750 io verion is = 12.2(35)SE5
how to add this switch in the existing two stack switches , with documentation
I have looked on notes to add a switch to an existing stack and haven’t identified answers on how the IOS will be affected on the new switch – will it downgrade to the current stack version or will the current stack upgrade to its version. At this moment in time I would prefer if the new switch IOS downgraded to the current stack IOS version.The new switch is a 3750V2 – will this affect how it joins the stack?The new switch has the image of IPBASEK9-M – again will this affect how it joins the stack?
I am having an issue with adding a c3750x switch to an existing switch stack Currently there is 2 x WS-C3750X-48P and I am trying to add another WS-C3750X-48P to this switch I have cabled the switch to the stack using the stack cables and added the command to provision the switch on the exisitng stack. However when I turn the switch on it just goes on its own stack.
I noticed the new switch had a later version of IOS so have downgraded this to the same version as the other switches but still no joy Here is the sh ver from the exisitng stack
uptime is 4 weeks, 4 days, 23 hours, 30 minutes System image file is "flash:/c3750e-universalk9-mz.122-53.SE2/c3750e-universalk9-mz.122-53.SE2.bin" License Level: ipbaseLicense Type: PermanentNext reload license Level: ipbase cisco WS-C3750X-48P (PowerPC405) processor (revision A0) with 262144K bytes of memory.Processor board ID FDO1448Z0FJLast reset from power-on21 Virtual Ethernet interfaces1 FastEthernet interface156 Gigabit Ethernet interfaces6 Ten Gigabit Ethernet interfacesThe password-recovery mechanism is enabled.
I am attempting to add and Catalyst 3750 - 12 port Gigabit switch to an existing stack of 3750 48 port switches (non-X fabric). I am not sure how to proceed. These are the two questions/thoughts I have. Any additional perspective I should have before proceeding.
What kind of configuration should I apply to the Gig switch before adding it to the stack?I am sure I will need to assign priority to the new switch, ideally, it will act as master.
We have a cisco stack with 5 ws-c3750-24p 12.2)55)SE3 c3750-ipbasek9-m switches. Can i add a switch to the stack that is the following model: ws-c3750g-48ts 12.2(25)see3 c3750-ipbase-m
I have a 3750G switch that can't detect another switch or be detected through its stack ports. I tried the recommended test; looping a cable between the ports and rebooting. I get the following message as the switch boots: SM: Detected stack cables at PORT1 PORT2. However, if I connnect another switch, it won't detect it and can't form a stack.
I'm trying to upgrade the IOS ver on a 3750G stack (2 switches), but the img on the switch is too old.The stack is running IOS c3750-i9-mz.121-19.EA1d.bin, and when I tried to upgrade to a newer version, I tried to go to IOS ver c3750-advipservicesk9-mz.122-35.SE5.bin since I need to enable ssh on the switch, but the switch did not reload.
Here's a prtscreen of the switch ver:
Cisco Internetwork Operating System Software IOS (tm) C3750 Software (C3750-I9-M), Version 12.1(19)EA1d, RELEASE SOFTWARE (fc1) Copyright (c) 1986-2004 by cisco Systems, Inc. Compiled Mon 05-Apr-04 22:40 by antonino Image text-base: 0x00003000, data-base: 0x007CBC3C
[code]...
what IOS ver can I upgrade to that is not already deferred?
I am currently having performance issues running a 3 x stack 3750G (different models) as a core for a network of roughly 12 x distribution switches. [code] As above, I have a 12 port Fibre switch and 2 x 3750G-48 port switches. [code] I tried to change the SDM to route but hit another issue where the 3750g-48 does not support SDM route so I had to revert back to desktop VLAN.Could the SDM Template be the reason for slow performance? If so which SDM Template should i use as this is the Core L3 switch.
Is that possible to configure a stack between then?
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ Tenho um cisco WS-C3750G-24TS com o IOS flash:/c3750-ipservicesk9-mz.1 22-25.SEB4.bin" Adquiri um novo cisco WS-C3750X-24 com o IOS flash:/c3750e-universalk9-mz.150-1.SE/c3750e-universalk9-mz.150-1.SE.bin.
I got Two Distribution Switches of Cisco 3750G. Each Distribution have two 3750G switches stacked. I also have one Cisco 3750V2 Access Switch connected to both Distribution. When I am checking for redundancy, I can only get redundancy test pass for one link not atall for other. If I have a link up with Distribution 1 only then its fine; but disappointment with Distribution 2 link. I can see that the switch priorities of Dist 2 is not correct ie. Master's priority is 10 and Member's is 15.
My question is that due to misconfigured priorities on Distribution 2 stack switches I am failing with redundancy if ONLY Dist 2 is up and Dist 1 is down.
I am running out of ports on a 4507R and would like to use a 3750G-24TS stack that I already have to expand capacity. Is it possible to configure EtherChannel between the 4507R and the 3750G stack and if so what is the best way to do it? without LACP, with active-active mode LACP or passive-active mode LACP...
This is what I have in mind:On the 4507R side I would like to use interface GigabitEthernet3/5 and interface GigabitEthernet4/5 where modules 3 and 4 on the 4507R are "6 1000BaseX (GBIC) (WS-X4306-GB)". On the 3750G side I would like to use ports 28 on both switches in the stack which are equipped with Cisco GLC-T= 1000BASE-T SFP transceiver module for Category 5 copper wire with RJ-45 connector. [URL] Cross-Stack EtherChannel Without PAgP or LACP should look like this:
is that what I should be doing? is there any benefit to the active-active mode LACP or passive-active mode LACP and which are applicable to the case above?
I have a stack of 3750G's where the connection between switch 1 port 1 and switch 2 port 2 are down
Stack Port Status Neighbors Switch# Port 1 Port 2 Port 1 Port 2 -------------------------------------------------------- 1 Down Ok None 3 2 Ok Down 3 None 3 Ok Ok 1 2
I have ruled out the stackwise cable as the problem but would like to know which switch has the problem
Running 12.2(53)SE2, IP base. Now I tried upgrading the firmware on the entire stack to 12.2(55)SE4 and ran into this error:(Command: archive download-sw /imageonly /overwrite /allow-feature-upgrade tftp://10.20.20.13/c3750e-universalk9-tar.122-55.SE4.tar)
Error: The image in the archive which would to used to upgade system number 2 does not support that system type.I haven't as yet removed the "3750G-24TS" switch from the stack and re-tried as yet, however, is the expectation that without the 24TS, the upgrade should work?
I have two 3750s stacked and one 3750 standalone all in one data closet. The both have the same versions. I want to combine them to make one stack. How do I force the standalone to be the master? sw 1 priority XX(Higher then the existing stack)? Both the stack and the standalone have management addresses. Would it be ok to delete the stack ip address? That way, the standalone(master's address will be the only management address)?How should I connect the standalone 3750 to the stack? At present, the 3750 stack is connected via a cascade cable going from the stack 1 port of the top switch to the stack 2 port of the bottom switch.
I had 2 3750 stacked and one of them decided to die (power supply) cisco replaced it and now i want to re-add that switch to stack. I have already upgraded my replacement switch to the same IOS version.I was reading that i can do it without powering down operational 3750 so the action plan so far is:
-power down NEW member -connect stacking cable -power up
as you can see my switch 2 is now a master and it still holds config of all Gi ports for switch 1. If i connect my NEW switch without any config (vlan.dat and startup-config) will my existing switch 2 copy all ports config to new switch ?
I need to add two additional 2960S switches to my stack. I saw a diagram that showed how a 4 switch stack can be connected, but I couldn't find much detail on adding a switch to an existing stack (besides master election). The output below shows how the existing stack is connected and its state
SW#sh switch detail Switch/Stack Mac Address : 0011.2222.3333 H/W Current
[Code].....
I will need to break one of the stack rings between SW1 and SW2 in order to connect the new switches. Does it really matter which ring I break to connect the additional switches? Does one ring act as primary? If so, I'd rather not break that ring so this process is transparent as possible. Also, is there any benefit to disabling the stack port vs just disconnecting the cable?
The company I work for owns a remote manufacturing facility that houses a stack of five 3750 switches that function as the core switching system for the plant. DHCP services are configured on the 3750 stack.
There are currently three VLANs configured, one for data and one for voice (144 and 244 respectively) and one for UCM servers (200), with corresponding subnets of 10.44.32.0 /19, 10.44.0.0 /19 and 10.44.100.0 /24.
The current DHCP scope configurations are as follows:
ip dhcp pool Plant-44_DHCP network 10.44.32.0 255.255.224.0 default-router 10.44.33.254
[Code].....
My question is will the addition of this scope in the manner presented cause any problems with PCs or IP phones outside the targeted recepents receiving the wrong IP information from this scope?
I plan to identify the users that should be members of this VLAN 444 and change the switchport mode access configuration on the corresponding switch ports from VLAN 144 to VLAN 444. The voice VLAN 244 will remain the same.
I have to add a 2960s PoE switch to an existing stack of two 2960s PoE switches. If The new switch has no configuration on it and the existing stack is broken by pulling te stack cables and then new cables are added and everything re-cabled correctly will the new switch assume the configuration from the stack without any issues?
I have a Catalyst 3750 I want to add to an existing stack (same models) through the stackwise port We use some complex QoS and other features on our network, and I'm not sure how much configuration I need to do on the new switch before adding it to the stack. Since this is going into an existing setup?
I am having a switch 3750G (WS-C3750G-24TS-S) running a software version (c3750-ipservicesk9-mz.122-55.SE6.bin) and using the PBR with IP SLA.While, i am applying it on interface, it says not supported....
route-map TO-CAS-E0 permit 10 match ip address 125 set ip next-hop verify-availability 10.116.199.200 10 track 100 (if i change this command to set ip next-hop 10.116.199.200, it works) ! WAN-L3-3750SW01(config-route-map)#interface GigabitEthernet1/0/11